QUESTION 1
You use Project Professional 2013 to manage a project that has customer-required milestone
completion dates. You need to see graphically that your milestones have slipped beyond your
customer-required dates. What should you add to the project milestones?

A. a Must finish on constraint
B. a finish date
C. a deadline
D. a Finish no later than constraint

Answer: C


QUESTION 2
You manage a project by using Project Professional 2013. Your project is updated with changes to
the baseline for selected tasks. You back up your project fife before you start your next tracking
cycle. After completing the tracking cycle, you notice that the baseline duration values on some
of the summary tasks are not correct. You need to correct these values before re-entering the
tracking data. You open the backed up version of the project schedule. What should you do next?

A. Manually update the summary tasks with the new duration values.
B. Reset the summary tasks to manual scheduling.
C. Ensure the tasks durations are of the same denomination values. Then reenter the tracking data.
D. Reset the baseline checking the Roll up baselines to all summary tasks option. Then reenter
the tracking data.

Answer: D


QUESTION 3
You are a program manager. Your project managers use Project Professional 2013 to manage
projects. The project managers want to utilize the same resources across their projects. You need
to combine the projects, as well as the project resources, to see allocations across the projects.
What should you do?

A. Copy and paste all resource assignments into a Master file.
B. Share resources from an external resource pool.
C. Create a Master project and insert subprojects by using Link to project.
D. Open all projects in a new window.

Answer: B


QUESTION 4
Your company uses Project Standard 2013 to track project progress. You need to accurately
calculate cost performance index (CPI) as a health indicator. Which three actions should you
perform? (Each correct answer presents part of the solution. Choose three.)

A. Ensure there is a value in the Status Date field.
B. Ensure there is a value in the Standard Rate field.
C. Ensure Task Dependencies exist in the schedule.
D. Enter actual progress information.
E. Level resources within available slack.

Answer: ABD


QUESTION 5
You are a project manager who uses Microsoft Excel 2013. Your company decides to migrate all of
the current projects in Microsoft Excel 2013 to Project Professional 2013. They allow all
employees to spend 8 hours migrating each project plan. Your current and unique project plan
has 462 tasks with duration in days, and resources have been assigned and named. You have a
status meeting in two days. You need to provide your project’s information by using Project
Professional 2013. What should you do?

A. Create a new project plan in Project Professional 2013 and use the Gantt Chart Wizard to
import from an Excel Workbook.
B. Rename the Excel file from .xlsx to .mpx, and open it by using Project Professional 2013,
activating the Mapping Excel Workbook feature. Map tasks, durations, and resources
assigned into Microsoft Project fields.
C. Open the Excel File .xlsx directly from Project Professional 2013, which will convert and map
tasks, durations, and resources assigned into Project fields.
D. Create a VBA macro by using the Excel Record Macro feature to import all tasks, durations,
and resources assigned from Excel into your new Project Professional 2013 project plan.

Answer: C

 